Quantcast

Lake County Gazette

Friday, November 22, 2024

VERNON HILLS PARK DISTRICT: Ranney & Donnelley Playground Update

Childrens playground 2154556 1920

Vernon Hills Park District issued the following announcement on June 4.

Ranney Playground project is set to begin with construction fencing on June 13 and playground removal June 14. 

Wood chip removal and site preparation will take place June 15-19. 

Playground installation is to begin June 20 and will take about 1 week. 

June 28 is scheduled to have engineered wood chips install. 

Playground audit to take place shortly afterwards. 

Playground may be open as soon as July 3.

Donnelley Playground project is set to begin with construction fencing on June 18. 

Playground removal will also begin on June 18. 

Wood chip removal and site preparation June 19- 25. 

Playground install set to begin June 26 and will take about 1 week. 

Engineered wood chips to be install July 2 or 3. 

Playground audit to take place shortly afterwards. 

Playground may be open as soon as July 10.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS